![]() |
Large
Infrastructure in Mathematics Enhanced Services Cellule MathDoc : management report |
Partner: UJF/MDC
Reporting Period: April - September 2003
From: Laurent Guillopé
E-mail: Laurent.Guillope@math.univ-nantes.fr
Telephone: +33 2 40379893
---------------------------------------------------------------
Work Carried Out:
WP-0: Project Management
Partners: All
Work done:
+ Preparation to den Haag meeting [CG, LG]
+ LIMES local administration [LG].
Estimated achievement:
+5%
-----------------------------------
WP-1: Quality of Data and Retrieval
Partners: FIZ, UJF, Eidetica, TUB; responsible: FIZ
------------
T1.3: Intermediate services evaluation,
revision of specifications
D1.3: Evaluation report, alpha versions,
and revised specifications
Work done:
+ ZMlinker
+ Tuning of the ZMATH matching application (tagged entries à la crossref)
(see http://adrar.ujf-grenoble.fr/ZMATH/zlink.html) [CG]
+ First prototype of ZMATH matching on unstructured references [CG]
+ edbm
+ preparation for upgrade to Ver. 2 of the software, with inclusion of
new data output structures, discussions with the FIZ partner
+ internal discussions [CG, LG, YL]
Estimated achievement:
------------
T1.4: Implementation of beta versions and integration into production process
D1.4: Production system incl. documentation
Work done: None
-----------------------------------
WP-2: National Access Nodes
Partners: FIZ, UJF, HMS, USDC, TUB, responsible: FIZ
T2.3: Incremental development of update procedures
D2.3: Update procedures including. Documentation
Work done: None
------------
T2.4: Extending the visibility and usability of the database
D2.4: Report on enhanced visibility, accessibility and usability
Work done: None
------------
T2.5: Integration with other national offers, network structure for information in
mathematics
D2.5: Integration with other national offers (service and report)
Work done: None
------------
T2.6: Development of license models, further contracts and other continuous co-operations
D2.6: Report on license and contractual matters, and other co-operations
Work done: None
-----------------------------------
WP-3: Distributed Editorial Units
Partners: FIZ, UJF, DTV, SIBA-UNILE, TUB; responsible: FIZ
T3.3: Installation and set up of basic technical functions for input procedures, start of
input
delivery
D3.3: Input environment including documentation
(due March 2001)
Work done: None
------------
T3.4: Improvement of existing functions and development of electronic reviewing tools
D3.4: Advanced input and reviewing facilities incl. documentation
(due March 2003)
Work done:
Work done:
+ Maintaining work flow for bibliographical data transmission to Berlin [LG]
+ preliminary steps for switching to xml format
Estimated achievement: + 5%
Estimated achievement:
------------
T3.5: Development of license models, further contracts and other continuous co-operations
D2.6: Report on license and contractual matters, and other co-operation
Work done: None
-----------------------------------
WP-4: Information Dissemination and Concertation
Partners: FIZ, Eidetica, DTV, SIBA-UNILE, HMS, USDC, TUB; responsible: TUB
T4.1: Public project WWW-server with project information
and public reports and Deliverables
D4.1: Public project WWW server (updated during the
whole duration of the project)
(due March 2004)
Work done: None
------------
T4.2: Periodical dissemination of information from the
project; Concertation events.
D4.2: List of publications and presentations at events
and workshops (due March 2004)
Work done: Participation to den Haag meeting
---------------------------------------------------------------
Project meetings attended:
7th LIMES project co-ordination meeting, Den Haag, 2-4 May 2003 [LG, CG]
Travels (other than project meetings):None
-----------------------------------
Problems: None
-----------------------------------
Other Comment: None
---------------------------------------------------------------
Costed Labour Resources:
WP-0: Project Management
Partners: All
Staff Category: Effort in hours
Engineer : 0
Scientist : 5
WP-1: Quality of Data and Retrieval
Partners: FIZ, UJF, Eidetica, TUB
Staff Category: Effort in hours
Engineer : 410
Scientist : 90
WP-2: National Access Nodes
Partners: FIZ, UJF, HMS, USDC, TUB
Staff Category: Effort in hours
Engineer : 0
Scientist : 15
WP-3: Distributed Editorial Units
Partners: FIZ, UJF, DTV, SIBA-UNILE, TUB
Staff Category: Effort in hours
Engineer : 0
Scientist : 0
WP-4: Information Dissemination and Concertation
Partners: FIZ, Eidetica, DTV, SIBA-UNILE, HMS, USDC, TUB
Staff Category: Effort in hours
Engineer : 20
Scientist : 20